76.962—Implementation and certification of compliance.
(a) Implementation.
A cable operator must implement remedial requirements, including prospective rate reductions and refunds, within 60 days from the date the Commission releases an order mandating a remedy.
(b) Certification of compliance.
A cable operator must certify to the Commission its compliance with any Commission order mandating remedial requirements. Such certification shall:
(1)
Be filed with the Commission within 90 days from the date the Commission releases an order mandating a remedy;
(2)
Reference the applicable Commission order;
(3)
State that the cable operator has complied fully with all provisions of the Commission's order;
(4)
Include a description of the precise measures the cable operator has taken to implement the remedies ordered by the Commission; and
(5)
Be signed by an authorized representative of the cable operator.