62.15040—What are the requirements for meeting increments of progress and achieving final compliance?
               		
               	 	
               	 	
               	 	               	 	               	 	               	 	               	 	
               	 	
    
        
        (a) Class I units.
         If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:
     
    
        
        (1) 
         Submit a final control plan.
     
    
        
        (2) 
         Submit a notification of retrofit contract award.
     
    
        
        (3) 
         Initiate onsite construction.
     
    
        
        (4) 
         Complete onsite construction.
     
    
        
        (5) 
         Achieve final compliance.
     
    
        
        (b) Class II units.
         If you plan to achieve compliance more than 1 year following the effective date of this subpart and a permit modification is not required, or more than 1 year following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet two increments of progress:
     
    
        
        (1) 
         Submit a final control plan.
     
    
        
        (2) 
         Achieve final compliance.