57.105—Submittal of required plans, proposals, and reports.
               		
               	 	
               	 	
               	 	               	 	               	 	               	 	               	 	
               	 	
    
        
        (a) 
         The failure of a smelter owner to submit any plan, report, document or proposal as required by its NSO or by this part shall constitute a violation of its NSO.
     
    
        
        (b) 
         If the Administrator determines that a nonferrous smelter is in violation of a requirement contained in an NSO approved under these regulations,  the Administrator shall, as provided by  section 119(f) of the Act:
     
    
        
        (1) 
         Enforce such requirement under  section 113 (a), (b), or (c) of the Act;
     
    
        
        (2) 
         Revoke the order after notice and opportunity for hearing;
     
    
        
        (3) 
         Give notice of noncompliance and commence action under  section 120 of the act; or
     
    
        
        (4) 
         Take any appropriate combinations of these actions.
     
    
        
        (c) 
         Under  section 304 of the Act, any person may commence a civil action against an owner or operator of a smelter which is alleged to be in violation or any order approved under this part.