(i) October 1, 2007 and October 1, 2008 |
50 percent of the amount that we calculated should be added under paragraph (a)(1) of this section. |
(ii) October 1, 2009 and October 1, 2010 |
75 percent of the amount that we calculated should be added under paragraph (a)(1) of this section. |
(iii) October 1, 2011 and continuing through September 30, 2022 |
100 percent of the amount that we calculated should be added under paragraph (a)(1) of this section as long as you have at least $3 million of Priority 1 and 2 coal problems remaining. |
(iv) October 1, 2022 and thereafter |
to the extent funds are available, 100 percent of the amount that we calculated should be added under paragraph (a)(1) until you have less than $3 million of Priority 1 and 2 coal problems remaining. |