You must include the following information in your DWOP:
(a)
A description and schematic of the typical wellbore, casing, and completion;
(b)
Structural design, fabrication, and installation information for each surface system, including host facilities;
(c)
Design, fabrication, and installation information on the mooring systems for each surface system;
(d)
Information on any active stationkeeping system(s) involving thrusters or other means of propulsion used with a surface system;
(e)
Information concerning the drilling and completion systems;
(f)
Design and fabrication information for each riser system (e.g., drilling, workover, production, and injection);
(g)
Pipeline information;
(h)
Information about the design, fabrication, and operation of an offtake system for transferring produced hydrocarbons to a transport vessel;
(i)
Information about subsea wells and associated systems that constitute all or part of a single project development covered by the DWOP;
(j)
Flow schematics and Safety Analysis Function Evaluation (SAFE) charts (API RP 14C, sub section 4.3c, incorporated by reference in § 250.198) of the production system from the Surface Controlled Subsurface Safety Valve (SCSSV) downstream to the first item of separation equipment;
(k)
A description of the surface/subsea safety system and emergency support systems to include a table that depicts what valves will close, at what times, and for what events or reasons;
(l)
A general description of the operating procedures, including a table summarizing the curtailment of production and offloading based on operational considerations;
(m)
A description of the facility installation and commissioning procedure;
(n)
A discussion of any new technology that affects hydrocarbon recovery systems;
(o)
A list of any alternate compliance procedures or departures for which you anticipate requesting approval; and
(p)
Payment of the service fee listed in § 250.125.