You must notify the appropriate MMS District Manager when you successfully complete or recomplete a well for production. You must:
    
    
        
        (a) 
         Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.
     
    
        
        (b) 
         Provide the following information in your notification:
     
    
        
        (1) 
         Lessee or operator name;
     
    
        
        (2) 
         Well number, lease number, and OCS area and block designations;
     
    
        
        (3) 
         Date you placed the well on production (indicate whether or not this is first production on the lease);
     
    
        
        (4) 
         Type of production; and
     
    
        
        (5) 
         Measured depth of the production interval.
     
    
        
            Code of Federal Regulations
        
        [71 FR 23862, Apr. 25, 2006]