250.195—What notification does MMS require on the production status of wells?

You must notify the appropriate MMS District Manager when you successfully complete or recomplete a well for production. You must:
(a) Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.
(b) Provide the following information in your notification:
(1) Lessee or operator name;
(2) Well number, lease number, and OCS area and block designations;
(3) Date you placed the well on production (indicate whether or not this is first production on the lease);
(4) Type of production; and
(5) Measured depth of the production interval.

Code of Federal Regulations

[71 FR 23862, Apr. 25, 2006]