(a)
For a well site, you must submit to the appropriate District Manager within 30 days after you complete the verification activities a form MMS-124, Application for Permit to Modify, to include the following information:
(1)
A signed certification that the well site area is cleared of all obstructions;
(2)
The date the verification work was performed and the vessel used;
(3)
The extent of the area surveyed;
(4)
The survey method used;
(5)
The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and
(6)
A post-trawling job plot or map showing the trawled area.
(b)
For a platform or other facility site, you must submit the following information to the appropriate Regional Supervisor within 30 days after you complete the verification activities:
(1)
A letter signed by an authorized company official certifying that the platform or other facility site area is cleared of all obstructions and that a company representative witnessed the verification activities;
(2)
A letter signed by an authorized official of the company that performed the verification work for you certifying that they cleared the platform or other facility site area of all obstructions;
(3)
The date the verification work was performed and the vessel used;
(4)
The extent of the area surveyed;
(5)
The survey method used;
(6)
The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and
(7)
A post-trawling job plot or map showing the trawled area.