The Regional Supervisor may grant a departure from the requirement to remove a platform or other facility by approving partial structure removal or toppling in place for conversion to an artificial reef if you meet the following conditions:
(a)
The structure becomes part of a State artificial reef program, and the responsible State agency acquires a permit from the U.S. Army Corps of Engineers and accepts title and liability for the structure; and
(b)
You satisfy any U.S. Coast Guard (USCG) navigational requirements for the structure.
Code of Federal Regulations
[67 FR 35406, May 17, 2002, as amended at 74 FR 19807, Apr. 29, 2009]