Decommissioning Applications and Reports Table
(a) Initial platform removal application [not required in the Gulf of Mexico OCS Region] |
In the Pacific OCS Region or Alaska OCS Region, submit the application to the Regional Supervisor at least 2 years before production is projected to cease |
Include information required under § 250.1726
. |
(b) Final removal application for a platform or other facility |
Before removing a platform or other facility in the Gulf of Mexico OCS Region, or not more than 2 years after the submittal of an initial platform removal application to the Pacific OCS Region and the Alaska OCS Region |
Include information required under § 250.1727
. |
(c) Post-removal report for a platform or other facility |
Within 30 days after you remove a platform or other facility |
Include information required under § 250.1729
. |
(d) Pipeline decommissioning application |
Before you decommission a pipeline |
Include information required under § 250.1751(a)
or § 250.1752(a)
, as applicable. |
(e) Post-pipeline decommissioning report |
Within 30 days after you decommission a pipeline |
Include information required under § 250.1753
. |
(f) Site clearance report for a platform or other facility |
Within 30 days after you complete site clearance verification activities |
Include information required under § 250.1743(b)
. |
(g) Form MMS-124, Application for Permit to Modify (APM). The submission of your APM must be accompanied by payment of the service fee listed in § 250.125
|
(1) Before you temporarily abandon or permanently plug a well or zone(2) Within 30 days after you plug a well * * *
|
Include information required under §§ 250.1712 and 250.1721
.Include information required under § 250.1717
.
|
|
(3) Before you install a subsea protective device |
Refer to § 250.1722(a)
. |
|
(4) Within 30 days after you complete a protective device trawl test |
Include information required under § 250.1722(d)
. |
|
(5) Before you remove any casing stub or mud line suspension equipment and any subsea protective device |
Refer to § 250.1723
. |
|
(6) Within 30 days after you complete site clearance verification activities |
Include information required under § 250.1743(a)
. |