Table 1
Critical actions as defined in § 55.2(b)(2)
|
Critical actions not allowed |
Critical actions not allowed |
Allowed if the proposed critical action is processed under § 55.20
1
|
Allowed if the proposed critical action is processed under § 55.20
1. |
Non-critical actions not excluded under § 55.12 (b) or (c)
|
Allowed only if the proposed action is a functionally dependent use and processed under § 55.20
1
|
Allowed only if the proposed action: (1) Is either (a) designed for location in a coastal high hazard area or (b) a functionally dependent use; and (2) is processed under § 55.20
1
|
Allowed if the proposed action is processed under § 55.20
1
|
Any non-critical action is allowed without processing under this part. |
1 Or those paragraphs of § 55.20
that are applicable to an action listed in § 55.12(a)
. |