(a) 
         For each Federal authorization—i.e., permit, special use authorization, certification, concurrence, opinion, or other approval—required under Federal law with respect to a natural gas project for which an application has been filed under  section 3 of the Natural Gas Act for a certificate of public convenience and necessity under  section 7 of the Natural Gas Act, each Federal agency or officer, or State agency or officer acting pursuant to delegated Federal authority, responsible for a Federal authorization must file with the Commission within 30 days of the date of receipt of a request for a Federal authorization, notice of the following:
     
    
        
        (1) 
         Whether the application is ready for processing, and if not, what additional information or materials will be necessary to assess the merits of the request;
     
    
        
        (2) 
         The time the agency or official will allot the applicant to provide the necessary additional information or materials;
     
    
        
        (3) 
         What, if any, studies will be necessary in order to evaluate the request;
     
    
        
        (4) 
         The anticipated effective date of the agency's or official's decision; and
     
    
        
        (5) 
         If applicable, the schedule set by Federal law for the agency or official to act.
     
    
        
        (b) 
         A Federal agency or officer, or State agency or officer acting pursuant to delegated Federal authority, considering a request for a Federal authorization that submits a data request to an applicant must file a copy of the data request with the Commission within 10 business days.
     
    
        
            Code of Federal Regulations
        
        [Order 687, 71 FR 62921, Oct. 27, 2006]