               	               		52.133—Relationship to other subparts.
               		
               	 	
               	 	
               	 	               	 	               	 	               	 	               	 	
               	 	
    
        
        (a) 
         This subpart applies to a person that requests a standard design approval from the NRC staff separately from an application for a construction permit filed under  10 CFR part 50 or a combined license filed under subpart C of this part. An applicant for a construction permit or combined license may reference a standard design approval.
     
    
        
        (b) 
         Subpart B of this part governs the certification by rulemaking of the design of a nuclear power plant. Subpart B may be used independently of the provisions in this subpart.
     
    
        
        (c) 
         Subpart F of this part governs the issuance of licenses to manufacture nuclear power reactors to be installed and operated at sites not identified in the manufacturing license application. Subpart F of this part may be used independently of the provisions in this subpart.